The city's schedule for this week has paving crews on Weston Road at night. Since November 15, the contractor has been milling and resurfacing the stretch between Royal Palm Boulevard and Meridian Parkway from 9 p.m. to 6 a.m. The city said that phase would take several weeks. A few miles west, Indian Trace was listed as substantially complete as of November 10, and the city expects no further traffic impacts there. Bonaventure Boulevard had its own night paving on the summer calendar.
All three of Weston's main roads were under construction in the same stretch of months, and the reason is financial. Two of the three projects are first-round awards from MAP Broward, the 30-year program funded by the Penny for Transportation surtax that Broward voters approved. On Weston Road, that money also pays for a lane layout change that drivers near Cleveland Clinic will notice long after the new asphalt fades.
A 2018 Ballot Is Paying for Most of It
The City of Weston's July 2025 MAP Broward update put the surtax approval in November 2018 and counted 13 Weston projects funded by that date, worth $25,143,158 in total. The two biggest pieces of this year's construction are on that list. In MAP Broward's municipal funding plan, revised October 15, 2025, Weston Road appears as project WEST-303 and Indian Trace as WEST-192. Both are Cycle 1 projects, both carry an "In Progress" status, and each was funded in two parts, one for design and one for construction.
| Corridor | Surtax design funding | Surtax construction funding | Total surtax award |
|---|---|---|---|
| Weston Road, WEST-303 | $588,000 | $4,312,000 | $4,900,000 |
| Indian Trace, WEST-192 | $369,600 | $3,091,549 | $3,461,149 |
Those are the funding-plan figures as of the October 2025 revision. Weston Road's construction contract is larger than its surtax share. The city puts the contract value at $6,141,991.98, and $4,312,000 of that comes from the surtax.
Weston has spent most of its surtax money below the pavement and above the intersections. The same city list includes a Weston Road adaptive signal control system at $6,070,000, plus fiber-optic networks on Weston Road at $3,470,000, Indian Trace at $2,080,000 and Royal Palm Boulevard at $2,210,000. Taken together, the signal and fiber awards are worth more than the two resurfacing awards combined. Some smaller awards are marked completed in MAP Broward's plan, including $1,612,082 for safety work at the Royal Palm Boulevard and Weston Road intersection, $319,086 for Lakeview Drive and $232,739 for citywide wayfinding.
Weston Road Gets a Lane Where One Used to Disappear
The city describes the Weston Road project, from Indian Trace to Griffin Road, as resetting the road's life cycle. In the same passage it names a safety fix: part of the road is being widened to remove an existing drop lane. The project FAQ gives the details. Northbound, the stretch in front of Cleveland Clinic from Cleveland Clinic Boulevard to South Commerce Parkway goes from two through lanes to three. Southbound, the widening covers about 500 feet on each side of West Corporate Lakes Boulevard.
That widening is why parts of Weston Road looked torn up long before any paving began. Pedrail Systems started the southbound widening the week of November 17, 2025. In early April 2026 it was finishing the new sidewalk on the west side and moving to the east side. Pedestrians between West Corporate Lakes Boulevard and South Commerce Parkway were sent to the west sidewalk while that work went on. The same April update scheduled foundation work for new signal mast arms at the South Commerce Parkway intersection. Anyone who used the Flanigan's lot north of Royal Palm this spring saw the drainage phase. Starting April 20, the northbound right-turn lane was closed in three stages, and the Flanigan's driveway itself closed for a day or two while traffic was sent north to North Commerce Parkway.
For an evening drive this season, the city's traffic notices put lane closures on weeknights between 9 p.m. and 6 a.m., with no full road closures and access to businesses and homes kept open. Bus riders should know that Broward County Transit Route 23 stop no. 5288, on southbound Weston Road just south of West Corporate Lakes Boulevard, was closed for roughly four months during construction, and the city pointed riders to the other stops along Weston Road. The project page lists Calvin Giordano and Associates as the consultant, and questions go to the city at 954-385-2600.
Indian Trace Is the Finished Example
Indian Trace shows what the full package looks like once the cones are gone. The project ran from Saddle Club Road east to the city limits at I-75. Along with the new surface, it widened the existing bike lanes into 7-foot buffered lanes and added accessible curb ramps at every existing intersection. It also changed the roadway drainage at two spots the city described as prone to standing water after heavy rain. School-year drivers will notice the new crossing-guard parking at the Saddle Club Road and Indian Trace intersection.
The work was split along a clear line. Paving east of Weston Road was done at night. West of Weston Road, crews worked by day, with lane closures limited to 9 a.m. to 4 p.m. and adjusted around school zones. The city's project page gives an estimated cost of $3,116,600 and names Pedrail Systems as the contractor, with EAC Consulting as the consultant. Weston Road has the same contractor, so the finished Indian Trace is a fair preview of what the Weston Road surface and markings will look like.
The buffered lanes join a bike network covered in our earlier look at where Weston's bike lanes end and the levee riding begins.
Bonaventure Boulevard Has a Second Project Coming
Bonaventure's resurfacing is not a surtax project in the city's materials. It covers Griffin Road to Indian Trace, with milling and resurfacing, new pavement markings, and repaired concrete sidewalks and curb ramps. The estimated cost is $2,610,533.84, and the contractor is Weekly Asphalt Paving. The city's June 5 notice scheduled night paving from June 7 through July 7, 2026. In September, the schedule called for weekday daytime lane closures at the Royal Palm Boulevard intersection and overnight closures at the bridge by Griffin Road. The project page lists October 2026 as the expected completion.
North of Indian Trace, Bonaventure gets its own project. The Bonaventure Boulevard Bike Lane project runs about 9,200 linear feet from Indian Trace north to State Road 84. It will widen, mill, resurface, stripe and sign the road, adding 5-foot bike lanes on both sides. Where the right of way or utility poles leave too little room, the plan calls for 4-foot bike lane keyholes instead. The money comes from a Federal Highway Administration grant through a Local Agency Program project, with an estimated cost of $478,081. Design was completed in September 2026, and the city expects construction to start in December 2026. If that schedule holds, Bonaventure residents will drive from one season of roadwork straight into the next.
The Smaller Streets on the List
Neighborhood streets have their own line items. MAP Broward's municipal program page lists three Weston rehabilitation and maintenance awards: $175,000 for Sagemont Way, $275,000 for Three Village Road, and $270,125 for pavement rehabilitation across the Bonaventure Development District. The city's own FY2026 adopted budget set aside $1 million for Phase II roadway milling and resurfacing, with a target date of September 30, 2026.
Saddle Club Road is the next corridor in design. The plan covers the road from west of Lakeview Drive to Weston Road, with widening and resurfacing, dedicated bike lanes, green conflict markings at crossings, new striping and signs, upgraded pedestrian signals and new ADA ramps. The city lists a design cost of $414,000 and a nine-month design phase. It is a Broward MPO CSLIP Cycle 3 project, so it is funded through a different program than the surtax. Families who use Saddle Club for the school run will see that work after the Indian Trace and Bonaventure projects.
For the weeks ahead, the practical calendar is this. Indian Trace is done. Weston Road night paving between Royal Palm and Meridian Parkway runs on weeknights. Bonaventure north of Indian Trace is next in line for construction. Anyone heading to a holiday event at Town Center after dark should plan around the Weston Road schedule, and our guide to this year's holiday calendar lists the dates that fall on those nights.
A rebuilt corridor changes how a street looks on a showing, from fresh striping to new sidewalks and smoother pavement out front. If you live on or near Indian Trace, Weston Road or Bonaventure and want to know how that fits into your home's presentation, The Scarberry Group is glad to help. Request a complimentary home valuation and staging consultation with Phyllis.